Extension to the Hong Kong
|
|
![]() The overall site layout from June 1995, when the building superstructure had just commenced. At this stage, the pair of 150m-long reinforced concrete cores is the most prominent structure at the site. |
![]() In this photo from September 1995, progress can be seen in the southern part of the building. The reinforced concrete core, which was constructed in stepped sections using a patented shuttering system, functioned efficiently after a three-month period of continual work. Some of the steel trusses for the floor structure of the Level 2 Exhibition Hall, including the first two pairs of supporting columns, was installed. To reduce construction costs, the floor slab of Level 1 Exhibition Hall was constructed of reinforced concrete (rather than structural steel) as there was no need to provide a large-span design for the ground floor area. |
![]() The southern portion of the reinforced concrete core topped out in November 1995. The erection of the steel decking for the floor slab was in full progress from the southern end to the seaward direction. The steel deck was concreted afterward to form a rigid composite floor structure. |
![]() In February 1996, less than 10 months from the commencement of the main building structure, the first section of the main roof truss was in position. The three levels of the Exhibition Hall, with the floor slab for Level 1 made of reinforced concrete, and Level 2 and 3 of structural steel construction, can be clearly seen in this photo. |
![]() July 1996: The construction of the linking bridge for the old and new convention and exhibition centre can be seen here. |
![]() A bird's eye view showing the entire roof structure in August 1996. The laying of the 750 mm multi-layered roof decking had just begun. |
![]() Close-up of the gigantic structural steel frame used to span the 80 m exhibition space between the pair of reinforced concrete cores. |
![]() The most difficult part of the installation: One of the 400-tonne main roof trusses is placed on a lifting girder in preparation for elevation to the top of the core wall. |
![]() Top-down view of the roof truss: The 20 m slot on the core wall provided towing access for the steel truss. This slot was reclaimed after the lifting process by the addition of reinforced concrete. Note the temporary unloading pier and the barge employed to deliver the roof trusses and other heavy components to the site. |
![]() Beginning stage for the shuttering system of the 150 m reinforced concrete core structure at the building's centre. The HKCECE project has a one-level partial basement which is mainly used for mechanical facilities; this made the construction process relatively uncomplicated |
![]() In a six-hour process, the roof truss was lifted to the top of the core wall by two pairs of strand-jacks. |
![]() The set-up of the strand-jack, its steel support columns, and the rail track facilitating the sideways sliding action of the steel truss can be seen in this photo. |
![]() Close-up of the strand-jack devices. After the lifting process, the jack would be temporarily removed so that it would not impede the sideways movement of the truss. |
![]() The first two trusses that are seen after braced with the fill-in members. An unobstructed 80 m space is not a easy distance to span using any lightweight structure. |
![]() The truss undergoing alignment on the top of the core wall. Using a synchronised horizontal jack on each end, the truss was pushed sideways until it reached the predetermined position on the core wall. |
![]() The first two trusses in position. The space between the steel trusses was braced with tie members which eventually unified the entire roof into a continual, eight-metre deep, two-way structure with an 80 m span. |
![]() Supporting detail of the roof truss. The weight of the main roof (about 4,200 tonnes excluding the apron areas) is supported by 24 bearer-plates which are rooted to the core wall structure. At this stage, the truss is temporarily rested on the bearers. It will be further adjusted by hydraulic jacks when the entire roof structure with all the articulating members is installed in its final position. |
![]() The gradual extension of the roof structure with the unit-by-unit addition of the prefabricated steel trusses. The floor below is of composite steel/reinforced concrete slab design. The rows of shallow trenches are the service channels, which are concealed in a raised floor system constructed of lightweight/expanded polystyrene filled concrete to be laid at a later stage. |
![]() The anchor bolts provided inside the concrete on top of the core wall for the support of the roof structure. |
![]() The connecting members for the multiple-curved apron of the roof stretching out from the main roof frame structure. |
![]() The complicated space inside the roof truss. The space here is eight metres deep on average, and curves to more than 15 metres deep in some sections. It will be provided with service-access in the form of a suspended cat-walk, and used mainly to accommodate building services such as distribution ductwork for the HVAC systems. |
![]() The suspended access gangway is erected using timber planks. It forms an elegant curve at the edge of the roof. |
![]() |
|
![]() |
Procedures to install the roof trusses
|
![]() The complicated geometry of the roof structure is shown here at the junction where two curved sections of the main roof and apron attachment meet. |
![]() The same portion of the roof with the undermost layer of galvanised steel deck panel installed. Access provision, basically in the form of bamboo scaffolding, is provided here. |
![]() The skeleton of the roof structure above the Grand Foyer. Although it gives a slender look from a distance, the actual structure is a heavy one. The worker in the photo indicates the scale and mass of the roof. |
![]() A typical junction inside the steel roof truss. At certain points, up to 16 steel members meet at one junction. The angles are awkward until the member reaches another connecting point opposite. The problem of dimensional co-ordination was a significant issue throughout the entire project. |
![]() The layout and basic structural arrangement of the main roof as seen from the cabin of the tower crane. |
|
![]() A portion of the partly finished, multi-layered roof deck as seen on a chilly winter dawn. |
![]() A splendid look at the two wings of the eastward-facing aprons during the erection of the roof decking system. |
![]() The 37,000 sq m roof surface needed finishing both on the top and on the underside. In the photo, workers are working on a temporary platform to install the metal-stripped soffit on the underside of the projecting roof apron. The purlin rail and bracket system that provide the shape and form of the final roof can also be seen. |
![]() Another complicated junction detail of the partly finished roof where three curved roof surfaces met. Naturally, this kind of junction formation together with the extraordinary large surface area of the roof created a drainage problem for rainwater; The only solution was effective waterproofing design. |
![]() |
|